| |
HORIZONTAL DIRECTIONAL DRILLING (HDD) |
Introduction |
|
Horizontal Directional Drilling (HDD) is a
trench less methodology that provides an installation alternative
that can offer a number of benefits over traditional open-cut.
HDD can be implemented with very little disruption to surface
activities, requires less working space, and may be performed
more quickly than open-cut methods. Also, it can simplify or eliminate
certain permitting processes. This type of installation of underground
infrastructure systems has seen a dramatic increase in recent
years.
|
Procedure |
-
HDD is a trench less construction method
that involves drilling a small pilot hole, using technology
that allows the drill to be steered and tracked from the surface.
The pilot bore is launched from the surface at an angle between
8 and 20 degrees to the horizontal, and transitions to horizontal
as the required depth is reached. A bore path of very gradual
curvature or near-straight alignment is normally followed
to minimize friction and to stay within the allowable joint
deflection and the allowable curve radius for the pipe. This
minimizes the chance of getting the pipeline “hung up”
in the soil or damaging the pipe.
- The pilot hole is enlarged by pulling back increasingly
larger reamers, or reaming heads, from the pipe insertion point
to the rig side. To achieve the appropriate bore path size it
may be necessary to perform several reaming operations. Generally,
all reaming procedures prior to the actual product installation
are referred to as pre-reams, and the final ream to which the
product pipe is attached is referred to as the back ream. After
the pre-reams, the pulling head and connecting product pipe
are attached to the reamer using a swivel, a device that isolates
the product pipe from the rotation of the HDD drill pipe. The
product pipe is then pulled behind the final reamer back through
the horizontal directional drill path to the exit pit on the
rig side.
|
Pipe Bursting |
- Utilizes a heavy-duty winch to pull a cracking
head that breaks the soil or other material into pieces
- Pipe is simultaneously pulled into the formed
void
- Allows use of larger diameter pipe
- Excavation limited to entrance and exit pits
as well as lateral connections
- Can also be used to replace lower lateral
|
Pipe Reaming |
- Utilizes a horizontal directional drilling
machine and modified cutter head
- Grinds existing pipe into smaller pieces that
are carried out with other excess materials by drilling fluid
to exit pit
- Pipe is simultaneously pulled into place
- Allows use of significantly larger diameter
pipe to replace existing pipe
- Excavation limited to entrance and exit pits
|
Horizontal Direction Drilling |
- Utilizes a horizontal directional drilling
machine to install a new pipe where no pipe currently exists
- Process starts with pilot hole drilled to desired
grade
- Hole is then enlarged by back reaming while
pipe is simultaneously pulled into place
- Utilizes a horizontal directional drilling
machine to install a new pipe where no pipe currently exists
- Process starts with pilot hole drilled to desired
grade
- Hole is then enlarged by back reaming while
pipe is simultaneously pulled into place
|
Advantages |
-
NAVIGATOR Horizontal Directional Drilling
units work by first drilling a pilot bore underground Different
drill heads are matched to the soil conditions and rock formations.
A "sonde" transmitter and receiver can be used for greater
accuracy, allowing the operator to steer the drill to avoid
other utilities or objects such as tree roots. Once the pilot
bore is complete a back reamer is attached to the drill string
and pulled back , enlarging the bore opening to accommodate
the conduit or pipe that is subsequently pulled into place.
No digging trenches. No Excavation. Minimun disruption!
-
The HDD method is extremely protective
towards the environment, causing no ecological damage at all.
Minimal damage to the area is only caused within the vicinity
of the unit. Several reasons also speak for the application
of the directional technique in central town areas.
- The normal course taken by the drilling operation
is described in the following: 1.Planning,preliminarysurvey
2. Selecting the drilling units and drilling tools
3. Pilot bore and detection
4. Back reaming (s) or upsizing bore(s)
5. Pulling in the pipe.
-
The high demands and expectations towards
the quality of the drilling job waiting to be done require
precise localization and steering. Localization is carried
out following the transmitter-receiver principle. One operator
follows the course of the bore head all the time. All measured
values are taken to protocol; directional corrections are
passed on to the machine operator via radiophone. It is also
possible to directly store the data found in this way, printing
them with the help of a PC or Laptop later on. Directional
control works according to the "clock-hand principle" via
slanted surface of the head; the head changes its direction
in correspondence with the clockwise direction.
|
Conclusions |
-
In case of canals and rivers it works very gently with out disturbing the water bed.
-
An other rule which is to be considered that every bore angle will be accurate enough that it will change its direction (horizontal) after the specified standards, after a specific distance, by the irrigation authority.
|
|
|
|